views
Karnataka Infrastructure Development Minister M B Patil on Friday said the work on the Bengaluru Suburban Rail Project corridor-2 between Benniganahalli and Chikkabanavara (25.01 km) will be completed within the set deadline of the next 26 months.
The Minister spoke to reporters after inspecting the progress of work along with Energy Minister K J George and K-RIDE officials. He also visited Lingarapuram, Shampura, Hebbal and Yeshawantpur.
”The BSRP project which runs parallel to the existing South-Western Railway lines has its challenges. However, these will be resolved to ensure completion of the project within 26 months,” Patil said.
The Minister said the officials have been instructed to work towards completing the works related to all four corridors by 2026. Even if it gets delayed due to some unforeseen reasons the project would be ready by 2028, he added.
According to him, the BSRP requires 157 acres of Railway land. He further said existing encroachments and structures on Railway land are being removed. Private land of about 5.11 acres required for laying of tracks has been acquired. Government land of about 2.72 acres has been acquired out of the total 7.73 acres.
Patil said Defence land of about 7.38 acres is required at three locations Jalahalli, Nagawara, and CQAE near Yeswanthpur. Working permission and in-principle approval has been obtained for these three locations from Defence Authorities.
Physical possession is yet to be handed over to KRIDE, Patil explained.
”So far, 10 to 15 per cent of work has been achieved related to corridor-2 and ground works will be over in the next 10 months. The ongoing RUB (Railway Under Bridge) at Shampura will also be completed by then,” the minister explained.
After completing Corridor-2, works related to Corridor-3 between Bengaluru and Devanahalli Airport and Corridor-4 between Kengeri and Whitefield will be taken up, Patil said.
He said a proposal has been sent to extend the BSRP to Chikkaballapura, Mysuru, Magadi, Tumakuru, Gowribidanuru, Kolara, and Hosuru. If this gets approved the BSRP would expand to a length of 452 km. Approval has been sought from Railways Department to conduct a pre-feasibility study regarding this.
Tenders have been invited to construct 12 stations under EPC mode (Engineering, Procurement, Construction) along the stretch of corridor 2 and the tender process will be finalised on August 31, Patil said.
The tender process for civil works of corridor-4 is over and bidders will be awarded the works soon. Supply of the first batch of 10 trains will begin in October. 2025, he added.
Comments
0 comment